Vernon Residents Get First Splash at New Active Living Centre This Sunday
VERNON, B.C. - Exactly 1,506 days after Vernon voters approved the project in a municipal referendum, and 965 days after crews officially broke ground, the wait to test out the city’s brand-new Active Living Centre (ALC) ends this Sunday, November 29, as the City of Vernon launches a two-week aquatic trial period ahead of the facility's full public opening.
According to an official release from the city, the sneak-peek phase invites community members to explore the new aquatic amenities at 3501 43rd Avenue through public swims, aquatic fitness classes, and learn-to-swim lessons.
While swimmers try out the pools, city staff will use the two-week window to fine-tune operations, test mechanical systems, and conduct planned operational exercises and emergency response drills.
Because systems and procedures are still being calibrated, the city notes that schedules and program offerings may shift slightly during the trial.
Admission during the preview period has been kept low:
Public swims: Free for ALC members and children under two, and $2 for all other swimmers.
Instructor-led programs: $2 per session for all participants.
Drop-ins are not permitted during the trial. Every participant must register individually in advance, either online at vernon.ca/poolschedule using a Vernon Recreation account, or in person at the Vernon Recreation Centre.
Meanwhile, preparations for the broader facility rollout continue.
Registration for January 2027 winter programs is already underway for Vernon residents and opens to non-residents on December 2, while limited-time founding member perks remain available for early sign-ups.
The milestone marks the culmination of a multi-year civic project that began when voters passed the Active Living Centre Loan Authorization Referendum on October 15, 2022.
Vernon City Council approved the finalized design, construction schedule, and $135.9-million maximum budget on April 8, 2024, the same day officials broke ground at the former Kin Race Track lands.
Built by Clark Builders and designed by Group2 Architecture using an Integrated Project Delivery model, the facility reached substantial completion on October 30, 2026.