Daily Closures, Bruhn Bridge, Scene of Fatal Semi-Truck Crash Last Summer, Being Replaced


Sicamous, BC - Starting November 25, full closures and single-lane alternating traffic will affect Highway 1 near Sicamous between Old Sicamous Road and Silver Sands Road.


Schedule of Traffic Disruptions


From November 17 to December 7, 2024, drivers should prepare for the following disruptions:

  • Full Closures:

    • Daytime: 9 a.m.–3 p.m.

    • Nighttime: 12 a.m.–4 a.m.

    • Full closures begin on November 25 and continue through November 30, resuming December 2–7. During closures, an alternate route will be available, with limited local traffic permitted at the top of each hour.

  • Single-Lane Alternating Traffic:

    • Daytime: 9 a.m.–3 p.m., with delays of up to 20 minutes.

      • Active November 18–23.

    • Nighttime: 8 p.m.–midnight, with delays of up to 30 minutes.

      • Active November 17–22 and November 24–29.


The RW Bruhn Bridge, the scene of a tragic semi-truck accident last summer that claimed one life and renewed concerns about its structural integrity, will now see significant traffic disruptions as construction ramps up on a long-anticipated replacement project.



As part of a Trans-Canada Highway improvement project, preparations are underway to replace the RW Bruhn Bridge with a modern four-lane structure.


The RW Bruhn Bridge replacement is part of a $260.5 million upgrade aimed at improving safety and traffic flow along the Trans-Canada Highway corridor.


The project includes four-laning a 1.9-kilometre stretch of Highway 1, enhancing local intersections, and providing safer routes for pedestrians and cyclists.


Construction is expected to continue through 2027.


Work is subject to change based on weather conditions. Check DriveBC for up-to-date information on closures and delays.